"SHSI Certificate of Recognition"
"Best on the Web"


Encyclopedia Dubuque

www.encyclopediadubuque.org

"Encyclopedia Dubuque is the online authority for all things Dubuque, written by the people who know the city best.”
Marshall Cohen—researcher and producer, CNN

Affiliated with the Local History Network of the State Historical Society of Iowa, and the Iowa Museum Association.




STEPHEN HEMPSTEAD HIGH SCHOOL

From Encyclopedia Dubuque
Revision as of 16:13, 17 April 2016 by Randylyon (talk | contribs)
Jump to navigationJump to search

STEPHEN HEMPSTEAD HIGH SCHOOL. Newest of Dubuque's senior high schools. Planning for the $5.7 million building began in the fall of 1966 with non-teaching, instructional, and administrative personnel encouraged to help design the building. A $6.7 million bond issue was approved in the spring of 1967.

Construction began in the fall of 1968. Classes scheduled to start in the new building in the fall of 1969 were not able to begin until the spring of 1970 due to bad weather and strikes. The official dedication of the building was held on October 25, 1970.

In April 1998 "Mustang Spirit," a sculpture of four spirited mustangs was unveiled at the school as a tribute to retiring principal Don Moody and soon to retire Bill Peck, Hempstead's assistant principal. The idea for the statue came from English teacher Ken Resch. The sculpture was based on a sketch by Hempstead senior Val Barbaro. Contributions came from students in a career orientation program and in National Honor Society. It was assembled with donated time from workers at JOHN DEERE DUBUQUE WORKS, a school partner. (1)

The new look of Hempstead in 2015. Photo courtesy: Dubuque Community School District
Photo courtesy: Dubuque Community School District
Photo courtesy: Dubuque Community School District
Photo courtesy: Dubuque Community School District
Open House/Dedication on October 3, 2015. Photo courtesy: Dubuque Community School District

In June 2015, the $30 million renovation of the high school was running ahead of schedule. Groundbreaking for the renovation and addition began in May 2013. Following the removal of the former auditorium, work on the administration wing began. A new auditorium and two music classrooms were completed near the beginning of the 2014-2015 school year. Work during the summer of 2015 was directed at completing new science classrooms and a business office for the high school in addition to improvement to the gymnasium and the career-and technical education areas. Work for the entire project was funded by a 1-cent sales tax. The work added 141,209-square feet to the building. (2)

See: DUBUQUE COMMUNITY SCHOOL DISTRICT





















---

Source:

1. Krapfl, Mike. "Sculpture Recognizes Moody's Leadership," Telegraph Herald, May 21, 1998, p. 3A. Online: https://news.google.com/newspapers?nid=aEyKTaVlRPYC&dat=19980521&printsec=frontpage&hl=en

2. Becker, Stacey. "Hempstead's $30 Million Facelift Nears Finish Line," Telegraph Herald, June 5, 2015, p. 1